Barnstaple power upgrade to support new homes and future demand
The biggest investment in Barnstaple's electricity network for decades is underway, improving the reliability of power supplies for thousands of customers while enabling hundreds of new homes in North Devon to connect to the grid.
Engineers are laying two kilometres of new underground cable between substations at Barnstaple Quay and Rock Park.
As well as a generational improvement to electricity supplies, the scheme will also provide the network capacity needed to connect the 345-home Mariners Haven development in Ilfracombe, supporting growth across North Devon.
The £2.5 million scheme, running parallel to the River Taw, takes in key areas of Barnstaple town centre, including The Strand, The Square, Commercial Road and Taw Vale.
Andrew Manning, Head of Operations for North Devon, said:
"This is one of the most significant investments in Barnstaple's electricity network in recent years and will help ensure many thousands of customers continue to enjoy reliable power supplies for decades to come.
"The project will also create the additional network capacity needed to support new homes and the transition to a more electric future, including electric vehicles and low-carbon heating.
“Given the scale of the work required, we have been working closely with the local authority to minimise disruption at this busy time of year. This includes reducing noise, maintaining access for businesses and making sure the public and our staff stay safe throughout the project.”
The cable-laying route goes through Rock Park, the town’s largest green space, where we are using directional drilling equipment to minimise disruption.
The kit allows engineers to install underground electricity cables by drilling beneath the ground instead of digging a continuous trench. This reduces the impact on the park and its users, while enabling cables to be installed safely.
The project, which is due to finish by April 2027, includes upgrades to equipment at the Rock Park substation to accommodate the new cabling.
The project is also delivering wider benefits for the community. As part of the work, engineers have installed additional electricity ducts needed for future reinforcement schemes, reducing the likelihood of further excavation work in coming years.
Teams have also supported the local authority by helping remove old tree stumps that had already been identified for clearance.
- About Us